Section 20 is a clause in the Landlord and Tenant Act 1985 which is intended to protect leaseholders from paying unnecessarily large sums for work carried out to their building.
If work should exceed £250 per leasehold, then we will arrange for a Section 20 to be raised. Here’s an overview of how the process works.
Stage One
For qualifying works, under Section 20 we will serve a “Notice of Intention to Carry Out Works” on all lessees. This Notice will describe the proposed works, state the reasons for considering the proposed works, and invite leaseholders to make written observations within 30 days.
Stage Two
At the end of the 30-day consultation period, we will have gained at least two estimates.
If nominations were made within the consultation period, then estimates will have been obtained from at least one of these nominations.
We will then provide a “Statement of Estimates,” which will set out the details of estimates we have obtained and a summary of any observations received within the consultation period.
All estimates obtained must be made available for inspection by the lessees, including estimates obtained from nominated contractors.
Stage Three
If, at the expiration of the consultation period, the chosen contractor did not provide the lowest estimate, then a “Notification of award of contract” will be served upon all lessees which will explain the reasons for not awarding the contract to the lowest estimate.
We will work closely with the contractors ensuring all works are carried out to the highest possible standard.